Search the Public Notice PortalMajor achievements have been reported in Stirling Council’s Capital Programme for 2026-27.
However, a number of projects are said to be facing adversity and need some attention.
This emerged in a report to the Finance, Economy and Culture Committee last Thursday.
Key achievements during the reporting period include continued construction progress on the Bridge of Allan Flood Protection Scheme; steady delivery of projects across the Roads Infrastructure Improvement Fund programme; advancement of road safety schemes.
There is also progress with packaging extended Producer Responsibility (pEPR) funded waste infrastructure projects; and, completion of the street lighting column replacement programme.
While the majority of projects remain on track, a number of delivery challenges are being actively managed, including Scottish Water dependency affecting one flood mitigation project, specialist contractor and geotechnical resource constraints affecting rockfall projects, and emerging cost pressures associated with the Balfron Household Waste Recycling Centre.
Priorities for the remainder of the financial year include maintaining delivery momentum across flood protection, roads infrastructure, bridge improvement and waste projects, progressing key procurement and construction activities, managing programme re-profiling where required, and making the most of benefits delivered through capital investment to communities across Stirling.
Major milestones racked up during the period so far include continued construction progress on the Bridge of Allan Flood Protection Scheme, completion of the Street Lighting Column Replacement Programme, and ongoing delivery of the Roads Infrastructure Improvement Fund programme.
A number of road safety and bridge projects have also advanced through design, procurement and some through construction stages, while pEPR-funded waste infrastructure initiatives and preparatory work for the proposed Balfron Household Waste Recycling Centre have continued to progress.
These achievements, say officers, demonstrate “sustained delivery across the capital programme” and support the council’s wider objectives of improving infrastructure resilience, community safety and environmental sustainability.
A number of major projects, the report reveals, have reached significant milestones during the reporting period.
Building on the successful completion and occupation of Callander Primary School and the second phase of the Bluebell House specialist ASN provision, significant progress continues to be made across the wider infrastructure portfolio.
Stirling Council.
The new Corbiewood Primary School is now approaching completion, with occupation programmed for November.
Progress has also been made on a number of strategic property and community projects, including advancement of the Central Library accessibility project where listed building and planning applications have been submitted, together with continued development of heritage, corporate property and investment projects.
Looking ahead, the council says the firm focus will be on maintaining delivery across the capital programme, ensuring that approved investment is translated into deliverable projects.